Agisoft Metashape

Agisoft Metashape => Feature Requests => Topic started by: bgreenstone on March 31, 2021, 08:45:57 PM

Title: Sequential Batch Operations
Post by: bgreenstone on March 31, 2021, 08:45:57 PM
I love Metashape, and I only have 1 issue with it:  the batch operations go in parallel instead of sequentially.  Right now if I have, say, 5 Chunks that I want to batch I have to wait for all of them to be completed at the same time instead of having the first one complete while it continues working on the next one.  This prevents me from doing any work until *all* of them have completed.

If Metashape's Batch function had an option to complete one Chunk at time it would help me tremendously!  Right now I have to wait hours for all of the Chunks to complete, but if it went one-by-one I could be working on one project while Metashape continues to work in the background.

Thanks,

-Brian
Title: Re: Sequential Batch Operations
Post by: Alexey Pasumansky on March 31, 2021, 09:46:29 PM
Hello Brian,

You can configure the batch in a way that all the steps are applied to the first chunk only, then to the second and etc.